NA
Back to ledger
B1Site developmentNeeds verification

Standard Power – NuScale and ENTRA1 sites

Announced Oct 6, 2023 Two planned data center energy facilitiesLast verified Aug 3, 2026

Contractual weight

B1 evidence

Standard Power announced planned facilities and selected technology and development partners, but no definitive offtake or construction contract is public.

Optioned MW is 24 disclosed 77 MW modules. No primary-source project update has confirmed a definitive agreement or current schedule.

Capacity

Capacity

MW firm
Not disclosed
MW optioned
1,848 MW

Record history

Status timeline

  1. Oct 6, 2023

    Deal announced

  2. No later public status change is recorded.

Provenance

Sources