B1Site developmentNeeds verification
Standard Power – NuScale and ENTRA1 sites
Announced Oct 6, 2023Two planned data center energy facilitiesAug 3, 2026

Firm capacity

Not disclosed

Optioned capacity

1,848 MW

Evidence assessment
What the public record supports, without upgrading incomplete claims.

Optioned MW is 24 disclosed 77 MW modules. No primary-source project update has confirmed a definitive agreement or current schedule.

Record history
Milestones remain visible when later evidence supersedes them.
  1. Announced

    Oct 6, 2023

  2. No later public status change is recorded.
Primary evidence
Open the cited record and verify the claim at its source.

Standard Power Chooses NuScale's Approved SMR Technology and ENTRA1 Energy to Energize Data Centers

NuScale Power · Oct 6, 2023

Supports: Partner selection, two planned sites, 24 modules at 77 MW each, data center purpose, and original 2029 target.

Open source