Back to atlas
B2Energy rights
Equinix – Oklo energy rights LOI
Announced Feb 16, 2024Covered U.S. facilities, subject to exclusionsAug 3, 2026

Firm capacity

Not disclosed

Optioned capacity

500 MW

Evidence assessment
What the public record supports, without upgrading incomplete claims.

Money moved, which raises the deal above an ordinary LOI, but the 500 MW remains a right rather than contracted delivery.

Record history
Milestones remain visible when later evidence supersedes them.
  1. Announced

    Feb 16, 2024

  2. No later public status change is recorded.
Primary evidence
Open the cited record and verify the claim at its source.

Equinix letter of intent to purchase power from Oklo

U.S. Securities and Exchange Commission · Feb 16, 2024

Supports: Executed LOI, 20-year contemplated PPAs, right of first refusal from 100 MW up to 500 MW, and site exclusions.

Open source

Oklo 2024 Form 10-K

U.S. Securities and Exchange Commission · Mar 24, 2025

Supports: $25 million payment, non-binding agreement risk, and requirement for later site-specific PPAs.

Open source