Google – TVA – Kairos Hermes 2 PPA
Announced Aug 18, 2025Hermes 2, Oak RidgeAug 3, 2026

Firm capacity

50 MW

Optioned capacity

Not disclosed

Evidence assessment
What the public record supports, without upgrading incomplete claims.

This is the first project-level implementation under the broader Google and Kairos fleet agreement.

Record history
Milestones remain visible when later evidence supersedes them.
  1. Announced

    Aug 18, 2025

  2. Updated

    Apr 17, 2026

    Kairos broke ground after receiving the NRC construction permit.

Primary evidence
Open the cited record and verify the claim at its source.

Google, Kairos Power, TVA Collaborate to Meet America's Growing Energy Needs

Kairos Power · Aug 18, 2025

Supports: Signed PPA, 50 MW output, Oak Ridge site, 2030 target, TVA delivery, and Google data center attribution.

Open source

Kairos Power Breaks Ground on Hermes 2 Demonstration Plant

Kairos Power · Apr 17, 2026

Supports: NRC construction permit and physical groundbreaking milestone.