B4Front-of-meter PPA

Google – TVA – Kairos Hermes 2 PPA

Announced Aug 18, 2025 Hermes 2, Oak RidgeLast verified Aug 3, 2026

Contractual weight

B4 evidence

Kairos and TVA signed a binding PPA, the NRC issued a construction permit, and Kairos broke ground on Hermes 2 in April 2026.

This is the first project-level implementation under the broader Google and Kairos fleet agreement.

Capacity

Capacity

MW firm
50 MW
MW optioned
Not disclosed

Record history

Status timeline

  1. Aug 18, 2025

    Deal announced

  2. Upgraded

    Apr 17, 2026

    Kairos broke ground after receiving the NRC construction permit.